Cladding remediation in Scotland: what the 2024 Act does for flats with unsafe external walls
The Grenfell Tower fire in London in June 2017 changed how the whole of the UK looks at the outside walls of tall residential buildings. Scotland had restricted flammable cladding on high-rise flats since 2005, but many flats had been built over three decades under earlier standards, and many owners found they could not sell or remortgage until someone proved their building was safe. The Scottish Parliament's answer is the Housing (Cladding Remediation) (Scotland) Act 2024. This article explains what the Act does, using the text of the Act and Scottish Government guidance as checked in November 2026.
Timeline
- 21 June 2024: the Act receives Royal Assent. Its interpretation and final provisions (Part 7) come into force the next day.
- 6 January 2025: the rest of the Act is commenced, giving Scottish Ministers their powers to assess and remediate buildings.
- Since then: the Scottish Government's Cladding Remediation Programme runs assessments and works under the Act; the responsible developers scheme provided for in Part 5 still needs regulations and consultation before it can start.
Which buildings are covered
Section 32 of the Act defines the buildings that can receive a single building assessment. All four conditions must be met:
- it is a flatted building containing at least one flat used, or intended to be used, as a home;
- it has an external wall cladding system;
- it stands 11 metres or more above the ground, measured from the lowest point of the adjacent ground and ignoring roof-top plant and a top storey that only houses plant;
- it was built, or otherwise developed, between 1 June 1992 and 1 June 2022.
Section 33 lets Ministers adjust or clarify these categories by regulations, but not extend the scheme to buildings that are not homes or that have no cladding. Offices, hotels and student blocks that are not dwellings fall outside it; so do houses and low-rise flats under 11 metres.
The single building assessment
At the heart of the system is the single building assessment (SBA). In the words of the Act, it assesses the risks to human life that the cladding creates or makes worse, and ends with a report identifying any work needed to eliminate or mitigate those risks. It must follow standards set by Ministers and be carried out by a person they have authorised.
In practice, the Scottish Government's specification, first published in June 2024 with independent fire engineers, combines two parts: a fire risk appraisal of external walls (FRAEW), which looks at the wall build-up itself, and a fire risk assessment (FRA) of the building as a whole, including escape routes and fire-stopping. Owners may hire any competent provider, but government funding is only available when the provider is on the official list of authorised SBA providers.
If new information comes to light after an SBA, for example when opening up the walls reveals something unexpected, Ministers can arrange an additional work assessment (section 34), which works the same way.
The Cladding Assurance Register
Part 1 of the Act requires Ministers to keep a Cladding Assurance Register. A building is entered once its SBA has been carried out. The entry records when the assessment took place and the work it identified; it is updated after any additional work assessment; and, once Ministers are satisfied that the work has been done, the date of that decision is added. Ministers may charge for access to the register, and section 2 makes it an offence to give false or misleading information for it.
The register matters most to people buying and selling flats. A building with a completed entry, showing either that no work is needed or that the identified work has been finished, gives lenders and conveyancers a single public reference instead of a patchwork of private reports.
Powers to act
Part 2 gives Ministers powers that go well beyond paying for surveys. They can:
- arrange an SBA or an additional work assessment, and require information for them (sections 3 to 5);
- arrange remediation work, and urgent remediation work where there is an immediate danger (sections 7 and 8);
- evacuate a building if it is too dangerous to stay, and arrange personal emergency evacuation plans for residents who need them (sections 9 and 11);
- obtain a warrant to enter premises by force where access is refused (section 14).
These powers exist because remediation of a block of flats needs every owner to agree, and in buildings with dozens of owners, absentee landlords or a disputed factor, that agreement can take years. The Act lets Ministers proceed where they cannot obtain consent. Owners can appeal against arranged remediation work (section 12), and Part 4 requires Ministers to engage with owners and occupiers before an assessment, to share the report afterwards, and to explain any work planned.
Who pays: the responsible developers scheme
Part 5 allows Ministers to set up a responsible developers scheme. Developers who join commit to fixing buildings they built; developers who are eligible but stay out go on a published prohibited developers list, and section 29 allows regulations to bar them from development, to stop building warrants being granted on their applications and to require verifiers to reject their completion certificates, the documents described in our article on building warrants in Scotland. This is the lever that makes membership attractive.
As of the Scottish Government's factsheet updated in October 2026, the scheme is not yet in force: its details still require further development and consultation before regulations are laid before the Scottish Parliament. Meanwhile, the government's position is that responsible developers agree to take forward and pay for the assessment and any remediation of their buildings, while public funding goes to owners such as social landlords, homeowners and factors who register an expression of interest and meet the programme's criteria.
What it means for the construction sector
- Developers and contractors who built flats over 11 metres between 1992 and 2022 should map their portfolio against the section 32 criteria now, because the scheme will ask them to take responsibility for buildings, not just for contracts still open.
- Fire engineers and surveyors are in demand: SBAs must follow a fixed specification, and only authorised providers qualify for government-funded work.
- Manufacturers and innovators working on wall systems, including the panelised and volumetric products described in our guide to modern methods of construction, face clients who now expect clear evidence of fire performance for the whole wall build-up, not just for individual components.
- New buildings are governed by the building standards, not by this Act. The Scottish Government notes that many flammable materials have been banned on multi-residential buildings over 18 metres since 2005, and a 2022 amendment to the Building (Scotland) Regulations banned highly combustible metal composite material in external wall cladding and as internal lining.
Progress reports
Section 30 requires Ministers to report on the progress of single building assessments and remediation work. These reports, and the quarterly programme updates the government publishes, are the best way to follow how many buildings have been assessed, how many need work and how many are finished. We do not repeat their figures here because they change every quarter; read the latest update directly.
Sources
- Housing (Cladding Remediation) (Scotland) Act 2024 (asp 7) — legislation.gov.uk, Parts 1, 2, 4, 5 and 7, sections 1, 2, 3–14, 30, 32–34 and 39 (consulted 12 November 2026).
- Scottish Government, Cladding Remediation Programme: factsheet (first published 15 October 2024, last updated 12 October 2026; consulted 12 November 2026).
- Scottish Government, Cladding Remediation Programme: Single Building Assessment specification (June 2024) and list of authorised SBA providers.