EV charge points in new Scottish buildings: what building standard 7.2 has required since April 2023

Published 2026-11-19

Most of the innovation centre's work on net zero dealt with the building itself: insulation, airtightness, heat pumps, factory-made panels. Since 2023 the Scottish building standards also reach the car park. The Building (Scotland) Amendment (No. 2) Regulations 2022 added a new mandatory standard, 7.2, which requires provision for charging electric vehicles wherever parking is built within the curtilage of a new building. This article explains what the standard and its guidance require, using the regulations and the domestic technical handbook as checked in November 2026.

The legal basis

The regulations (SSI 2022/349) were made on 22 November 2022 and came into force on 3 April 2023. They insert standard 7.2 into schedule 5 of the Building (Scotland) Regulations 2004, in section 7 (sustainability), alongside the existing statement of sustainability in standard 7.1. The mandatory text is short:

"Every building must be designed and constructed in such a way that provision for the charging of electric vehicles is made where car parking spaces are located within the building or the curtilage of the building."

Two limitations follow. The standard does not apply to a non-domestic building with ten or fewer parking spaces, and it does not apply to alterations or extensions, except "major renovation works". The same regulations also apply the standard to certain conversions: those that change the number of dwellings or separate units in a building, turn a residential building into another type of building, or turn a building into a residential one.

The Scottish Government's policy note explains the aim: transport was Scotland's largest source of greenhouse gas emissions, and the government wanted people to have convenient charging "at home, at work and when out and about". Like every building standard, 7.2 is checked through the building warrant process: the charging provision is shown on the warrant drawings and confirmed at completion.

What a new home needs

The detail is in the domestic technical handbook (June 2023 edition, clause 7.2.1). It distinguishes two cases.

DevelopmentCharge pointsEnabling infrastructure
Single dwelling with parking in its curtilage (not a garage)At least one charge point socket of 7 kW or more, next to the parking spaceNot separately required
Building with more than one dwelling and shared parkingOne 7 kW socket per dwelling, up to the number of parking spaces, plus one for every four accessible spaces not already servedDucting to every parking space in the curtilage

The handbook's own example: a building of 25 flats with 35 open-air parking spaces, two of them accessible, needs 26 spaces with a charge point socket (one per flat plus one for the accessible spaces) and enabling infrastructure only for the remaining nine. Spaces inside a covered car park, defined as parking within the footprint of a building such as a garage or an underground or roof-top car park, are excluded from the charge point count. A household with two cars is expected to manage with one socket.

The guidance specifies the equipment as well as the number. Charge points should follow BS EN 61851, deliver at least 7 kW from each socket simultaneously, have a universal (untethered) socket and a status indicator, and be at least a Mode 3 system on a dedicated circuit. Installation must meet BS 7671 and the IET code of practice for electric vehicle charging equipment. Positions matter too: cables should not cross footpaths, cycle routes or dropped kerbs, and the handbook gives clearances around floor-mounted and wall-mounted units.

Ducts for the future

Where a socket is not fitted, "enabling infrastructure" means the ducts or other containment from a suitable electricity supply point to each future charge point, with space planned for any switchgear. The aim is that a charger can be added later without builder work other than at the point of installation. Each future position should carry durable signage reading "Dedicated position for electric vehicle charge point", and the home's quick-start guide, required under standard 6.8, should describe the installation.

The cost cap

The standard is not meant to force grid reinforcement at any price. The handbook treats sockets as cost-effective where the extra cost of the electricity supply to the site does not exceed an average of £2,000 (excluding VAT) per socket. If it would, the developer installs the enabling infrastructure instead, and as many sockets as the cap allows. To rely on this, the warrant applicant should provide at least two written quotations, one of them from the Distribution Network Operator, showing the connection cost with and without the chargers and the maximum number of sockets that fits within the cap.

The handbook also reminds installers that the network operator must be told about a charge point added to an existing supply or included in an application for a new one, a step that affects programme as well as cost on larger sites.

Major renovations and mixed developments

For existing buildings the standard bites only on major renovation works, which the regulations define as renovation of a building with ten or more parking spaces where more than 25% of the surface area of the building envelope is renovated and the works include the parking or its electrical infrastructure. The handbook adds that work whose main purpose is fire safety, such as replacing unsafe cladding, counts as remediation rather than renovation; projects under the cladding remediation programme do not trigger the standard on that basis alone.

In a domestic major renovation the same pattern applies, ducts to every space and a socket per dwelling, but only where the existing supply has capacity after the works, and subject to a different limit: the installation is considered cost-effective up to 7% of the total capital cost of the renovation. On sites that combine homes and non-domestic buildings, the warrant application must say which parking spaces belong to which building, and each part follows its own technical handbook.

What it means for the construction sector

Standard 7.2 does not require anyone to provide parking. Scottish policy, as the handbook notes, still puts walking, cycling and public transport first; the standard applies only where parking is built.